Co-O Gold project progressing well.

Error message

Notice: Undefined index: form_build_id in ajax_get_form() (line 320 of /srv/arccon.com.au/www/includes/ajax.inc).

Arccon are pleased to announce that the Co-O Gold project is progressing well.

Earthworks are completed, along with the new leach tank which is commissioned and already operating. 

The following will be ready for commissioning in February:

•         HV Switchyard upgrade 

•         Mine switch yard electrical upgrade

•         Mine compressor room electrical upgrade

•         CIL stage 1 tank farm upgrade

•         Thickener upgrade stage 1

Concrete works will be completed in early March, with SMP works and the Sag mill installation underway.